Edit Schedules |
1 - Click in the New schedule box and enter a new name.
2 - Modify the interval by using the slider buttons.
Note: The left slider button specify the start time: this is the scheduled time when the interval becomes valid. Specify the end time by using the right slider button: this is the scheduled time when the interval is no longer valid .
3 - Check the days of the week and the holidays for which the schedule applies. You can also use the dotted buttons to make multi-selections:
•
: Select all days of the week and the four holidays
•
:Select all seven days of the week.
•
: Select only business days (Monday to Friday).
•
: Select only the four holidays.
4 - Click the Add Interval button to add a new interval to the schedule. To remove an interval, select it and click the Remove Interval button.
5 - Once your schedule selection is complete, click Save or Cancel to return to the Schedule configuration window.
1 - Click in the schedule name box at the top right section and modify the name if needed.
2 - Modify the intervals by using the slider buttons.
Note: The left slider button specify the start time: this is the scheduled time when the interval becomes valid. Specify the end time by using the right slider button: this is the scheduled time when the interval is no longer valid .
3 - For each interval to modify, check the days of the week and the holidays for which the schedule applies. You can also use the dotted buttons to make multi-selections:
•
: Select all days of the week and the four holidays
•
:Select all seven days of the week.
•
: Select only business days (Monday to Friday).
•
: Select only the four holidays.
4 - Click the Add Interval button to add a new interval to the schedule. To remove an interval, select it and click the Remove Interval button.
5 - Once your schedule selection is complete, click Save or Cancel to return to the Schedule configuration window.